- HOMEWelcome
- DIRECTORATE FOR EU AFFAIRSStructure
- E.U.Structure
- TÜRKİYE-EU RELATIONS
- History of Türkiye- EU Relations
- Main Documents
- Agreements
- Protocols
- Accession Partnership Documents
- National Programmes for the Adoption of the Acquis (NPAA)
- Türkiye Reports Prepared by the European Commission
- Enlargement Strategy Papers
- Türkiye’s National Action Plan for the EU Accession
- Türkiye’s National Action Plan for the EU Accession (2021-2023)
- Association Council Decisions
- Documents on Türkiye-EU Summits
- Institutional Structure
- Customs Union
- Türkiye- EU High Level Dialogue Meetings
- DATASources
- MEDIANews
- CONTACTContact Us
Doğubayazıt Wastewater Project
GENERAL INFORMATION |
|
Project title |
Doğubayazıt Wastewater Project |
Priority area |
Water (infrastructure related activities) / Environment and Climate Action |
Beneficiary |
Doğubayazıt Municipality |
Co-Beneficiary |
- |
Duration |
Wastewater Treatment Plant 26 months December 2021 – February 2024
Sewerage and Stormwater Network Systems 24 months December 2021 – February 2024 |
EU contribution (Euro) |
16.250.0000 |
|
|
PROJECT SUMMARY |
|
Brief description of the project and main objectives |
Construction of wastewater treatment plant, sewerage and stormwater network systems. Developing a feasible wastewater management system by providing sewerage and stormwater network and wastewater treatment plant that provides reduction of pollution of receiving environment. |
Location |
Doğubayazıt (Ağrı) |
Achievements / expected outputs |
Wastewater treatment plant, sewerage and stormwater network systems. With the construction of the wastewater treatment plant, sewerage and stormwater network systems, the needs of the region in terms of wastewater management will be met until 2050. |