TÜRKÇE
  Updated: 04/03/2022

Niksar Integrated Water Project

 

 

GENERAL INFORMATION
 

Project title
 

Niksar Integrated Water Project

Priority area
 

Water (infrastructure related activities) / Environment and Climate Action

Beneficiary

Niksar Municipality

Co-Beneficiary
 

-

Duration

Wastewater Treatment Plant 24 months

April 2021 – April 2023

 

Water Supply and Wastewater Collection Systems 24 months

May 2020 – May 2022

EU contribution (Euro)

24.088.0000

 

 

 

 

PROJECT SUMMARY

Brief description of the project and main objectives
 

Construction of wastewater treatment plant, water supply and wastewater collection systems.

Improving the water quality of Kelkit creek via reducing pollution load caused by untreated wastewater discharge in the existing situation and contribute to improvement of public health.

Overcoming the operational problems in the sewerage system through construction of wastewater network.

Location

Niksar (Tokat)

Achievements / expected outputs

Wastewater treatment plant, water supply and wastewater collection systems.

With the construction of the wastewater treatment plant, the needs of the region in terms of wastewater treatment services will be met until 2047.



Updated: 04/03/2022 / Hit: 3,229